Bathroom Rebuild in Bonogin

A Bonogin bathroom stripped back to the frame: framing straightened and levelled, and the floor slab prepared with reinforcing mesh.

This Bonogin bathroom had been stripped right back to the frame. Before any new walls or tiles go on, the structure has to be straight and solid.

I checked and levelled the wall framing with a laser and a long level, so the new linings and tiles will sit flat. On the floor, I tied reinforcing mesh into the slab section around the new floor waste, ready for the concrete.

Dan from SURVE levelling bathroom wall framing with a laser and long level in BonoginDan from SURVE tying reinforcing mesh around a new floor waste in a Bonogin bathroom slabDan from SURVE tying reinforcing into a bathroom slab in Bonogin

How I prepare a bathroom for new walls and floors

  1. Strip back to the frame and check it for rot, damage and movement.
  2. Straighten and level the framing, packing or replacing studs where needed.
  3. Add noggins and supports for fittings, vanities and grab rails.
  4. Prepare the floor section with reinforcing mesh, ready for concrete.
  5. Keep the site tidy and protected between stages.

Need something similar done in Bonogin? I’m Dan, a licensed tradesman and former builder with 35+ years in the building industry. See my handyman services in Bonogin, or get a free quote. You can also call Sue on 0435 207 771.